I suspect your chassis will arrive very late this year or sometime in the first quarter of 2023. These delays are beyond our control as right now Chevy seems to be the only one delivering anything remotely on time, and they are still delayed.

We continue to track these units weekly as soon as I see movement on any end I’ll update you with better dates.

I would plan for deliveries in Mid 2023 currently.